Bookmark Jamaica-Gleaner.com
Go-Jamaica Gleaner Classifieds Discover Jamaica Youth Link Jamaica
Business Directory Go Shopping inns of jamaica Local Communities

Home
Lead Stories
News
Business
Sport
Commentary
Letters
Entertainment
The Shipping Industry
The Star
E-Financial Gleaner
Overseas News
The Voice
Communities
Hospitality Jamaica
Google
Web
Jamaica- gleaner.com

Archives
1998 - Now (HTML)
1834 - Now (PDF)
Services
Find a Jamaican
Library
Live Radio
Weather
Subscriptions
News by E-mail
Newsletter
Print Subscriptions
Interactive
Chat
Dating & Love
Free Email
Guestbook
ScreenSavers
Submit a Letter
WebCam
Weekly Poll
About Us
Advertising
Gleaner Company
Contact Us
Other News
Stabroek News

Overruns tag Government contracts in Jamaica
published: Tuesday | March 14, 2006

Tyrone Reid, Staff Reporter

THE 18TH Annual Report of the Contractor-General, which spans the period January to December 2004, has revealed that the bulk of Government contracts are characterised by significant overruns.

Greg Christie, Contractor General, in this latest submission to Parliament, said that while the pre-tender process had improved, the management of the post-award segments continues to be problematic.

"The majority of works contracts reflect significant overruns in both the budgeted costs and the scheduled delivery time," read a section of the detailed report.

The report raised particular concern about contracts tendered in 2002 to repair flood-damaged roads that are currently at various stages of completion.

"Some of these contracts have either been terminated, re-tendered or are still in progress," the document stated.

The Office of the Contractor General revealed that the monitoring of contracts and projects during the stated period showed that some contracts, which commenced in 2002 and are scheduled for completion in 2003, were yet to be completed.

Mr. Christie outlined that the overruns were mainly due to a failure by both the client agencies and the contractors to deploy adequate resources to properly capitalise the projects.

Another factor was the suitability of the contractors and consultants/project managers. Mr. Christie recommended that the choices be based on an objective assessment of their experience and capabilities.

Also in the report, the Contractor General reiterated to Parliament the importance of proper planning and realistic time and cost budgets.

Mr. Christie also pointed out that there was a lingering perception that the Government's Procurement Procedures were still not being adhered to, especially as it relates to contracts below $4 million.

He said the efforts of his office to ascertain the value and total number of contracts between $250,000 and $3,999,000 failed. "To date, there has been negligible response from the entities from whom we have requested this information," the report said.

More Lead Stories



Print this Page

Letters to the Editor

Most Popular Stories


































© Copyright 1997-2006 Gleaner Company Ltd.
Contact Us | Privacy Policy | Disclaimer | Letters to the Editor | Suggestions | Add our RSS feed
Home - Jamaica Gleaner